In 2009, the average cost to construct a 150,000-barrel-a-day oil refinery was $2.4 billion (excluding any interest
Question:
In 2009, the average cost to construct a 150,000-barrel-a-day oil refinery was $2.4 billion (excluding any interest payments). This capital investment is spread uniformly over a five-year construction cycle (i.e., the refinery starts producing products in 2014). Assume end-of-year cash-flow convention and answer the following questions.
a. If the cost of capital spent to build the refinery is 10% per year, how much interest will be charged (as a lump sum in 2014) during the construction of this project?
b. If the cost-capacity factor is 0.91, what is the approximate cost to build a 200,000-barrel-a-day refinery in 2009?
c. If inflation of the construction cost of a refinery is 9.2% per year, what is the estimated cost of building a 200,000-barrel-a-day refinery in 2019?
Cost of capital refers to the opportunity cost of making a specific investment . Cost of capital (COC) is the rate of return that a firm must earn on its project investments to maintain its market value and attract funds. COC is the required rate of...