In the following table, project activities in days are listed with three time estimates for duration in

Question:

In the following table, project activities in days are listed with three time estimates for duration in days and predecessors for the activities.


In the following table, project activities in days are listed


(a) Calculate the expected time of each activity using MSP.
(b) Construct a Gantt chart using MSP.
(c) Use MSP to draw a network diagram.
(d) Assuming the default 5-day workweek, calculate the critical path of the project.
(e) Calculate the slack for theactivities.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management A Managerial Approach

ISBN: 978-0470226216

7th Edition

Authors: Jack R. Meredith, Samuel J. Mantel,

Question Posted: