Question: Industrial Construction Co. wanted to raise money to construct a canning factory in Wisconsin. Various persons promised to subscribe the needed amount, which they agreed
Industrial Construction Co. wanted to raise money to construct a canning factory in Wisconsin. Various persons promised to subscribe the needed amount, which they agreed to pay when the construction was completed. The construction company assigned its rights and delegated its duties under the agreement to Johnson, who then built the cannery. Vickers, one of the subscribers, refused to pay the amount that he had subscribed on the ground that the contract could not be assigned. Was he correct?
Step by Step Solution
3.37 Rating (156 Votes )
There are 3 Steps involved in it
Vickers was correct Because the construction of the canning factory called for the skill and expe... View full answer