Industrial Construction Co. wanted to raise money to construct a canning factory in Wisconsin. Various persons promised

Question:

Industrial Construction Co. wanted to raise money to construct a canning factory in Wisconsin. Various persons promised to subscribe the needed amount, which they agreed to pay when the construction was completed. The construction company assigned its rights and delegated its duties under the agreement to Johnson, who then built the cannery. Vickers, one of the subscribers, refused to pay the amount that he had subscribed on the ground that the contract could not be assigned. Was he correct?

408 Part 2 Contracts Appendix

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Anderson's Business Law And The Legal Environment

ISBN: 9780324638189

20th Edition

Authors: David P Twomey, Marianne M Jennings, Ivan Fox

Question Posted: