Question: Kieu Corporation constructs a new warehouse. It pays $100,000 for materials and $70,000 to the general contractor. Architectural fees total $18,000. The corporation pays $13,000
Kieu Corporation constructs a new warehouse. It pays $100,000 for materials and $70,000 to the general contractor. Architectural fees total $18,000. The corporation pays $13,000 in interest on its loan to finance construction. The land costs $15,000, and the real estate taxes paid on the land during construction amount to $1,000. What is Kieu’s initial basis in the warehouse?
Step by Step Solution
3.44 Rating (163 Votes )
There are 3 Steps involved in it
Kieus initial cost basis in the warehouse is 201000 and 15000 in the land Taxpay... View full answer