Label each of the following statements about the PERT three-estimate approach as true or false, and then
Question:
(a) Activity durations are assumed to be no larger than the optimistic estimate and no smaller than the pessimistic estimate.
(b) Activity durations are assumed to have a normal distribution.
(c) The mean critical path is assumed to always require the minimum elapsed time of any path through the project network.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction to Operations Research
ISBN: 978-1259162985
10th edition
Authors: Frederick S. Hillier, Gerald J. Lieberman
Question Posted: