The Lockhead Aircraft Co. is ready to begin a project to develop a new fighter airplane for
Question:
The project involves 10 activities (labeled A, B, . . . , J), where their precedence relationships are shown in the following project network.
Using the PERT three-estimate approach, the usual three estimates of the duration of each activity have been obtained as given below.
(a) Find the estimate of the mean and variance of the duration of each activity.
(b) Find the mean critical path.
(c) Find the approximate probability that the project will finish within 100 weeks.
(d) Is the approximate probability obtained in part (c) likely to be higher or lower than the true value?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Introduction to Operations Research
ISBN: 978-1259162985
10th edition
Authors: Frederick S. Hillier, Gerald J. Lieberman
Question Posted: