The Lockhead Aircraft Co. is ready to begin a project to develop a new fighter airplane for

Question:

The Lockhead Aircraft Co. is ready to begin a project to develop a new fighter airplane for the U.S. Air Force. The company€™s contract with the Department of Defense calls for project completion within 100 weeks, with penalties imposed for late delivery.
The project involves 10 activities (labeled A, B, . . . , J), where their precedence relationships are shown in the following project network.
The Lockhead Aircraft Co. is ready to begin a project

Using the PERT three-estimate approach, the usual three estimates of the duration of each activity have been obtained as given below.

The Lockhead Aircraft Co. is ready to begin a project

(a) Find the estimate of the mean and variance of the duration of each activity.
(b) Find the mean critical path.
(c) Find the approximate probability that the project will finish within 100 weeks.
(d) Is the approximate probability obtained in part (c) likely to be higher or lower than the true value?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Introduction to Operations Research

ISBN: 978-1259162985

10th edition

Authors: Frederick S. Hillier, Gerald J. Lieberman

Question Posted: