Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer
Question:
Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported:
Inspection time . . . . . . . 0.5 days
Process time . . . . . . . . . 2.8 days
Wait time . . . . . . . . . . . . 16.0 days
Queue time . . . . . . . . . . 4.0 days
Move time . . . . . . . . . . . 0.7 days
Required:
1. Compute the throughput time.
2. Compute the manufacturing cycle efficiency (MCE) for the quarter.
3. What percentage of the throughput time was spent in non-value-added activities?
4. Compute the delivery cycle time.
5. If by using Lean Production all queue time can be eliminated in production, what will be the new MCE?