Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer

Question:

Lipex, Ltd., of Birmingham, England, is interested in cutting the amount of time between when a customer places an order and when the order is completed. For the first quarter of the year, the following data were reported:

Inspection time . . . . . . . 0.5 days

Process time . . . . . . . . . 2.8 days

Wait time . . . . . . . . . . . . 16.0 days

Queue time . . . . . . . . . . 4.0 days

Move time . . . . . . . . . . . 0.7 days


Required:

1. Compute the throughput time.

2. Compute the manufacturing cycle efficiency (MCE) for the quarter.

3. What percentage of the throughput time was spent in non-value-added activities?

4. Compute the delivery cycle time.

5. If by using Lean Production all queue time can be eliminated in production, what will be the new MCE?


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Accounting

ISBN: 9780073526706

12th Edition

Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer

Question Posted: