Management at Webster, in Problem is now concerned as to whether caulking tubes are being properly capped.
Question:
Management at Webster, in Problem is now concerned as to whether caulking tubes are being properly capped. If a significant proportion of the tubes are not being sealed. Webster is placing its customers in a messy situation. Tubes are packaged in large boxes of 144. Several boxes are inspected, and the following numbers of leaking tubes are found:
Calculate p-chart three-sigma control limits to assess whether the capping process is in statistical control.