Marc Smith's construction firm currently has three projects under way in various counties in Iowa. Each requires

Question:

Marc Smith's construction firm currently has three projects under way in various counties in Iowa. Each requires a specific supply of gravel. Three gravel pits are available in Iowa to provide for Smith's needs, but shipping costs differ from location to location. The following table summarizes the problem Smith faces. Determine the optimal shipping assignment so as to minimize totalcosts:

Marc Smith's construction firm currently has three projects unde
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Quantitative Analysis For Management

ISBN: 162

11th Edition

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

Question Posted: