Mary is planning her wedding and develops the following preliminary information. For this problem, the normal times
Question:
For this problem, the normal times have been changed from OM3
a. Draw the network for this project.
b. What is the critical path(s)?
c. What is the project completion time?
d. What activity has the most slack?
e. What wedding activities did Mary leave out of her analysis? List them and now redraw the project network (but do NOT try to assign activity times or work out the new solution). What did you learn?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
OM operations management
ISBN: 978-1285451374
5th edition
Authors: David Alan Collier, James R. Evans
Question Posted: