Question:
This morning, ten jobs have been released to the shop by the ERP system, and the production manager is interested in minimizing the time it takes to complete the entire schedule, usually referred to as the schedule make span. The following table gives the number of hours required for each operation.
What sequence achieves the minimum make span and what is the minimum length of a schedule?