Activity______________________________________________________Time to Complete
Materials moved to production floor..........................................................30 minutes
Production in station 1........................................................................63 minutes
Materials moved to station 2..................................................................11 minutes
Wait to begin at station 2......................................................................15 minutes
Production in station 2.......................................................................114 minutes
Inspection........................................................................................5 minutes
Materials moved to finished goods inventory.............................................12 minutes
Required
a. What is the manufacturing cycle time (throughput time) to produce a batch of 1-inch plant flats and prepare it for sale?
b. How much of the process time is value-added?
c. Calculate the manufacturing cycle efficiency.
d. What suggestions do you have for eliminating non-value-added time?