On December 31, 2007, LAS1 Construction entered into a major long-term construction project with the following terms.
Question:
Total contract price ....... $3,000,000
Total expected cost ....... $2,4000,000
Construction is expected to take 3 years. Production costs and cash flows are shown in the following table.
(a) Show the gross profit for each year under both the percentage-of-completion and completed-contract methods.
(b) Assume that total projected costs increase by $100,000, and the company makes the change in estimate at December 31, 2008. Compute the gross profit for 2008 under the revised assumption.
(CFAadapted)
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Intermediate Accounting principles and analysis
ISBN: 978-0471737933
2nd Edition
Authors: Terry d. Warfield, jerry j. weygandt, Donald e. kieso
Question Posted: