On February 1, 2007, Amanda Beard Construction Company obtained a contract to build an athletic stadium. The

Question:

On February 1, 2007, Amanda Beard Construction Company obtained a contract to build an athletic stadium. The stadium was to be built at a total cost of $5,400,000 and was scheduled for completion by September 1, 2009. One clause of the contract stated that Beard was to deduct $15,000 from the $6,600,000 billing price for each week that completion was delayed. Completion was delayed 6 weeks, which resulted in a $90,000 penalty. Below are the data pertaining to the construction period.


On February 1, 2007, Amanda Beard Construction Company obtained


Instructions
Using the percentage-of-completion method, compute the estimated gross profit recognized in the years2007–2009.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting principles and analysis

ISBN: 978-0471737933

2nd Edition

Authors: Terry d. Warfield, jerry j. weygandt, Donald e. kieso

Question Posted: