On February 1, 2013, Arrow Construction Company entered into a three-year construction contract to build a bridge

Question:

On February 1, 2013, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2013, costs of $2,000,000 were incurred with estimated costs of

$4,000,000 yet to be incurred. Billings of $2,500,000 were sent and cash collected was $2,250,000.

In 2014, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2014 billings were $2,750,000 and $2,475,000 cash was collected. The project was completed in 2015 after additional costs of $3,800,000 were incurred. The company's fiscal year-end is December 31. Arrow uses the percentage-ofcompletion method.

Required:

1. Calculate the amount of gross profit or loss to be recognized in each of the three years.

2. Prepare journal entries for 2013 and 2014 to record the transactions described (credit various accounts for construction costs incurred).

3. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2013 and 2014.


Balance Sheet
Balance sheet is a statement of the financial position of a business that list all the assets, liabilities, and owner’s equity and shareholder’s equity at a particular point of time. A balance sheet is also called as a “statement of financial...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate accounting

ISBN: 978-0077647094

7th edition

Authors: J. David Spiceland, James Sepe, Mark Nelson

Question Posted: