On March 15, 2010, Frankel Construction contracted to build a shopping center at a contract price of

Question:

On March 15, 2010, Frankel Construction contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals actual) cash collections and contract costs follows:


On March 15, 2010, Frankel Construction contracted to build a


a. Calculate the amount of revenue, expense, and income for each of the three years 2010 through 2012 using (1) the percentage-of-completion method, (2) the completed contract method, and (3) the installment method.
b. Discuss which method you believe provides the best measure of the construction company's performance under thiscontract?