Phase I of a program has just been completed successfully. The customer, however, was displeased because he

Question:

Phase I of a program has just been completed successfully. The customer, however, was displeased because he always had to wait three weeks to a month after all tests were complete before data were supplied by the contractor. For Phase II of the program, the customer is requiring that advanced quality control procedures be adhered to. This permits the customer’s quality control people to observe all testing and obtain all of the raw data at the same time the contractor does. Is there anything wrong with this arrangement?