Pine Village needs some additional recreation fields. Construction will cost $225,000 and annual O&M expenses are $85,000.

Question:

Pine Village needs some additional recreation fields. Construction will cost $225,000 and annual O&M expenses are $85,000. The city council estimates that the value of added youth leagues is about $190,000. Annually In year 6 another $75,000 will be needed to refurbish the fields. The salvage value is estimated to be $100,000 after 10 years. Draw the cash flow diagram.