Product A is an end item and is made from two units of B and four of
Question:
A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks.
a. Show the bill- of- materials (product structure tree).
b. If 100 units of A are required in Week 10, develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.