Reconsider the project outlined in problem 1. Management would like to complete the project in less than

Question:

Reconsider the project outlined in problem 1. Management would like to complete the project in less than 12 weeks. Management has determined that activity C can be crashed 4 weeks, for a total cost of $10,000. No other activities can be crashed. Will crashing activity C meet management’s goal of less than 12 weeks? Why or why not?