Reddy Heaters, Inc., produces insert heaters that can be used for various applications, ranging from coffeepots to
Question:
Sheri: Doug, I think we have some real concerns that need to be addressed. Production is down, employee morale is low, and the number of defective units that we have to scrap is way up. In fact, over the past several years, our scrap rate has increased from 9 percent to 15 percent of total production. And scrap is expensive. We don’t detect defective units until the end of the process. By that time, we lose everything. The nature of the product simply doesn’t permit rework.
Doug: I have a feeling that the increased scrap rate is related to the morale problem you’ve encountered. Do you have any feel for why morale is low?
Sheri: I get the feeling that boredom is a factor. Many employees don’t feel challenged by their work. Also, with the decline in performance, they are receiving more pressure from their supervisors, which simply aggravates the problem.
Doug: What other problems have you detected?
Sheri: Well, much of our market share has been lost to foreign competitors. The time it takes us to process an order, from receipt to delivery, has increased from 20 to 30 days. Some of the customers we have lost have switched to Japanese suppliers, from whom they receive heaters in less than 15 days. Added to this delay in our delivery is an increase in the number of complaints about poorly performing heaters. Our quality has definitely taken a nosedive over the past several years.
Doug: It’s amazing that it has taken us this long to spot these problems. It’s incredible to me that the Japanese can deliver a part faster than we can, even in our more efficient days. I wonder what their secret is.
Sheri: I investigated that very issue. It appears that they can produce and deliver their heaters rapidly because they use a JIT purchasing and manufacturing system.
Doug: Can we use this system to increase our competitive ability?
Sheri: I think so, but we’ll need to hire a consultant to tell us how to do it. Also, it might be a good idea to try it out on only one of our major product lines. I suggest the small heater line. It is having the most problems and has been showing a loss for the past two years. If JIT can restore this line to a competitive mode, then it’ll work for the other lines as well.
Within a week, Reddy Heaters hired the services of a large CPA firm. The firm sent Kim Burnham, one of its managers, to do the initial background work. After spending some time at the plant, Kim wrote up the following description of the small heater production process:
The various departments are scattered throughout the factory. Labor is specialized and trained to operate the machines in the respective departments. Additionally, the company has a centralized stores area that provides the raw materials for production, a centralized maintenance department that has responsibility for maintaining all production equipment, and a group of laborers responsible for moving the partially completed units from department to department.
Under the current method of production, small heaters pass through several departments, where each department has a collection of similar machines. The first department cuts a metal pipe into one of three lengths: three, four, or five inches long. The cut pipe is then taken to the laser department, where the part number is printed on the pipe. In another department, ceramic cylinders—cut to smaller lengths than the pipe—are wrapped with a fine wire (using a wrapping machine). The pipe and the wrapped ceramic cylinders are then taken to the welding department, where the wrapped ceramic cylinders are placed inside the pipe, centered, and filled with a substance that prevents electricity from reaching the metal pipe. Finally, the ends of the pipe are welded shut with two wire leads protruding from one end. This completed heater is then transferred to the testing department, which uses special equipment to see if the heater functions properly.
The small heaters are produced in batches of 300. It takes 50 hours to cut 300 metal pipes and prepare 300 ceramic cylinders (1/6 hr. per unit, both processes occurring at the same time). After 50 hours of production time, the 300 metal pipes are transported to the laser department (20 minutes transport time), and the 300 ceramic cylinders are transported to the welding department (20 minutes transport time). In the laser department, it takes 50 hours to imprint the part number (1/6 hr. per pipe). The 300 metal pipes are then transported to the welding department. In the welding department, the ceramic and metal pipes are joined and welded. The welding process takes 50 hours (1/6 hr. per pipe). Finally, the 300 units are transported (20 minutes) to the testing department.
Each unit requires 1/6 hour for testing, or a total of 50 hours for the 300 units. From start to finish, the total production time for the 300 units is as follows:
Cutting and ceramic .... 50 hrs
Laser ........ 50
Welding ....... 50
Testing ........ 50
Moving ......... 1
Total time ....... 201 hrs.
Notice that laser must wait 50 hours before it can begin imprinting. Similarly, welding must wait 100 hours before it can begin working on the batch, and finally, testing must wait 150 hours before it can begin working on the batch.
Based on the information gathered, Kim estimated that the production time for 300 units could be cut from 201 hours to about 50 hours by creating a small heater manufacturing cell.
Required:
1. One of the first actions taken by Reddy Heaters was to organize a manufacturing cell for the small heater line. Describe how you would organize the manufacturing cell. How does it differ from the traditional arrangement? Will any training costs be associated with the transition to JIT? Explain.
2. Explain, with computational support, how the production time for 300 units can be reduced to about 50 hours. If this is a true reduction in production time, what implications does it have for Reddy’s competitive position?
3. Describe the organizational and operational activities that must be managed to bring about the reduction in production time. What are the cost drivers associated with these activities? For operational drivers, indicate the expected effect on activity costs.
4. Initially, the employees resented the change to JIT. After a small period of time, however, morale improved significantly. Explain why the change to JIT increased employee morale.
5. Within a few months, Reddy was able to offer a lower price for its small heaters. Additionally, the number of complaints about the performance of the small heaters declined sharply. By the end of the second year, the product line was reporting profits greater than had ever been achieved. Discuss the JIT features that may have made the lower price and higher profits possible.
6. Within a year of the JIT installation, Reddy’s controller remarked, “We have a much better idea than ever before of what it is costing us to produce these small insert heaters.” Offer some justification for the controller’s statement.
7. Discuss the impact that JIT has on other management accounting practices.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Cost Management Accounting And Control
ISBN: 101
6th Edition
Authors: Don R. Hansen, Maryanne M. Mowen, Liming Guan
Question Posted: