Refer to Problem 12. Assume drat unusually mild weather has caused a change in the quantity and

Question:

Refer to Problem 12. Assume drat unusually mild weather has caused a change in the quantity and timing of orders for golf carts. The revised plan calls for 100 golf carts at the start of week 6, 100 at the start of week 8, and 100 at the start of week 9.
a. Determine the timing and quantities for orders for Top and Base.
b. Assume that equipment problems have reduced the manufacturer€™s capacity for assembling Bases to 50 units per week. Revise your material requirements plan for Base to reflect this, but still meet delivery dates.
In problem
Refer to Problem 12. Assume drat unusually mild weather has