Refer to the data provided in Cornerstone Exercise 10-24. Required: Calculate the labor rate and efficiency variances

Question:

Refer to the data provided in Cornerstone Exercise 10-24.


Required:

Calculate the labor rate and efficiency variances using the columnar and formula approaches.


 Exercise 10-24

Lata, Inc. produces aluminum cans. Each can has a standard labor requirement of .03 hours. During the month of April, 250,000 cans were produced using 7,000 labor hours @ $9.00. The standard wage rate is $8.50 per hour.