Referring to Figure 12.22, how would splitting Activity 3 on July 1 to complete Activity 4 and

Question:

Referring to Figure 12.22, how would splitting Activity 3 on July 1 to complete Activity 4 and then finish Activity 3 affect the revised project completion date? Show your work. Do you recommend splitting Activity 3 or allow Susan to first complete it and then perform Activity 4? Which strategy would allow the project to finish sooner? Why?