Resolve the earned value example of Table 10-1 by re-computing Figures (a) and (b) using the 0100%rule.
Question:
Transcribed Image Text:
Table 10-1 Earned Value Example (today is day 7) ActiityPredecessorDays Duation Budget, S Actual Cost, $ 680 270 600 300 800 400 400 4 3 4 567 8 9 10 300 300 150 150 400 200 200 200 Total 300 300 550 150 200 400 | 400 | 200 Cum. . 300 300 6001150 1300 1500 1500 1900 2300 2500 Total Figure Example baseline (PV) budget using the 50-50 rule. 0 1 23 4 5 67 8 910 300 150 150 400 EV 300 550 150 200 Cum. EVİ 300 | 300 | 300 | 600 | 1150| 1300|1500 Cost Cum. AC00680 680 950 950 gure
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 41% (12 reviews)
This table shows the result of the 0100 rule Note that the actuals accrue in the same manner as the ...View the full answer
Answered By
Sinmon Warui Kamau
After moving up and down looking for a job, a friend introduced me to freelance writing. I started with content writing and later navigated to academic writing. I love writing because apart from making a living out of it, it is also a method of learning and helping others to learn.
5.00+
40+ Reviews
45+ Question Solved
Related Book For
Project Management A Managerial Approach
ISBN: 978-0470226216
7th Edition
Authors: Jack R. Meredith, Samuel J. Mantel,
Question Posted:
Students also viewed these Management Leadership questions
-
Resolve Problem 27 using the 50-50 rule for planned value and earned value?
-
Table 1 shows a rule base with four rules about boiler maintenance and their prior probabilities and Bayes factors obtained from historical data. No probability value is provided for R4 because it is...
-
Using information from Table 10.2 in Chapter 10 about capital market history, determine the return on a portfolio that is equally invested in Canadian common stocks and bonds. What is the return on a...
-
Darrel & Co. makes electronic components. Chris Darrel, the president, recently instructed Vice President Jim Bruegger to develop a total quality control program. If we dont at least match the...
-
You've collected the following information about Erna, Inc.: Sales = $275,000 Net income = $19,000 Dividends = $8,100 Total debt = $67,000 Total equity = $91,000 What is the sustainable growth rate...
-
What is the value of k? A) B) C) D) 5/3
-
1 Can you compare your approach with that of other companies in which colleagues on your course work? Does this suggest any plausible alternative ways of managing internationally? How much scope do...
-
Ritz Company had the following shares outstanding and retained earnings at December 31, 2015: Preferred shares, 8% (par value $ 25; outstanding, 9,000 shares) ..... $ 225,000 Common shares...
-
Item 8 Part 2 of 6 2 . 1 7 points Return to questionItem 8 Required information Required information Skip to question [ The following information applies to the questions displayed below. ] Daily...
-
Prepare journal entries for the purchase of a grader for $375,000: Purchased from the General Operating Fund. Purchased from the Equipment Reserve Paid by the General Operating Cash Account but...
-
Resolve Problem 8b using MSP. Omit the calculations for CPI, SPI, and CSI. Problem 8b Repeat the calculations in a, but now using the % Complete column. Assume that the PV values are based on time...
-
Repeat Problem 11 using the time proportionality rule and the following new data for % completion of each task: a: 100; b: 100; c: 80; d: 25; e: 0.
-
Write a general expression for the yield on any debt security (rd) and define these terms: real risk-free rate of interest (r*), inflation premium (IP), default risk premium (DRP), liquidity premium...
-
How do you demonstrate resilience as a leader during times of crisis or uncertainty, and what steps do you take to bolster your team's resilience ?
-
What would you do if it becomes clear to you that the potential successor you were grooming is not going to make the grade as a supervisor? What are your next steps? Do you think this grooming is...
-
How do services and products differ? What kind of decisions do companies make regarding products and services? Why are brands important to marketers? How do marketing strategies change during the...
-
What leadership principles do you feel you possess that are important for APRNs to exhibit? What principles do you need to explore to be more confident in performing? Which leadership style do you...
-
Question 1- Where do you go in the Courier to find out your amount of leftover inventory for a specific product last round? Based on the production tab of the worksheet I gave you; how do you use...
-
Greyson Grinding Company produces an abrasive powder in a grinding process. This process had an inventory at the beginning of February, to which Greyson had assigned the following costs: Direct tate...
-
What are bounds and what do companies do with them?
-
Repeat Problem 19 with the same game costing $3.50 for each play. Data from Problem 19 After paying $4 to play, a single fair die is rolled, and you are paid back the number of dollars corresponding...
-
What do the Schedule Performance Index (SPI) and the CostPerformance Index (CPI) demonstrate? How can a project manager use this information to estimate future project performance?
-
Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the...
-
Suppose you have a project with a Budget at Completion (BAC) of $250,000 and a projected length of 10 months. After tracking the project for six months, you have collected the information in the...
-
Suppose the S&P 500 currently has a level of 960. One contract of S&P 500 index futures has a size of $250 S&P 500 index. You wish to hedge an $800,000-portfolio that has a beta of 1.2. (A)In order...
-
Exhibit 4.1 The balance sheet and income statement shown below are for Koski Inc. Note that the firm has no amortization charges, it does not lease any assets, none of its debt must be retired during...
-
Haley is 57 years of age. She is planning for future long-term care needs. She knows that yearly nursing home costs in her area are currently $69,000, with prices increased by 5 percent annually....
Study smarter with the SolutionInn App