SCHEDULE OF COST OF GOODS MANUFACTURED The following information is supplied for Sanchez Welding and Manufacturing Company.
Question:
SCHEDULE OF COST OF GOODS MANUFACTURED The following information is supplied for Sanchez Welding and Manufacturing Company. Prepare a schedule of cost of goods manufactured for the year ended December 31, 20--. Assume that all materials inventory items are direct materials.
Work in process, January 1 .....$20,500
Materials inventory, January 1 .....11,000
Materials purchases ..........12,000
Materials inventory, December 31 ..13,000
Direct labor .............9,500
Overhead .............5,500
Work in process, December 31 ....10,500