Sieverville Machine Company has developed the following standard factory overhead costs for each SX unit assembled in
Question:
During August, 38,000 units of SX were actually produced. Actual direct labor hours totaled 77,500, and actual factory overhead totaled $700,000.
Required:
Determine the overall factory overhead variance and analyze it with each of the following variance analysis methods, indicating whether the variances computed are favorable or unfavorable.
(1) Two-variance method, for controllable and volume variances.
(2) Three-variance method, for spending, variable efficiency, and volume variances.