Larabee Ltd prepared a budget for the production of 300 units in April 2004 as follows.

The production for the month was 400 units and the costs were as follows.


Required 

(a) Calculate the following variances for April 2004: 

(i) Direct material usage 

(ii) Direct material price 

(iii) Direct labour efficiency 

(iv) Direct labour rate. 

(b) Comment on the variances in (a) and suggest possible causes.