The 100% rule suggests that before a PERT chart is done, a project manager must: a. make

Question:

The 100% rule suggests that before a PERT chart is done, a project manager must:

a. make sure 100 percent of the project is funded.

b. make sure the project team is devoted solely, or 100 percent, to the project.

c. make sure that each person on the project team got 100 percent on his or her project management final exam.

d. make sure 100 percent of the project tasks are defined.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Accounting Information Systems

ISBN: 9781266370373

4th Edition

Authors: Vernon Richardson, Chengyee Chang, Rod Smith

Question Posted: