The critical path in a PERT chart represents: a. the sequencing of tasks. b. the most important
Question:
The critical path in a PERT chart represents:
a. the sequencing of tasks.
b. the most important tasks of the whole project.
c. the longest path of tasks needed for project completion.
d. the tasks that must be completed without errors.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 100% (QA)
c the longest path of tasks needed for project completion In a PERT Program Evaluation and Rev...View the full answer
Answered By
Asim farooq
I have done MS finance and expertise in the field of Accounting, finance, cost accounting, security analysis and portfolio management and management, MS office is at my fingertips, I want my client to take advantage of my practical knowledge. I have been mentoring my client on a freelancer website from last two years, Currently I am working in Telecom company as a financial analyst and before that working as an accountant with Pepsi for one year. I also join a nonprofit organization as a finance assistant to my job duties are making payment to client after tax calculation, I have started my professional career from teaching I was teaching to a master's level student for two years in the evening.
My Expert Service
Financial accounting, Financial management, Cost accounting, Human resource management, Business communication and report writing. Financial accounting : • Journal entries • Financial statements including balance sheet, Profit & Loss account, Cash flow statement • Adjustment entries • Ratio analysis • Accounting concepts • Single entry accounting • Double entry accounting • Bills of exchange • Bank reconciliation statements Cost accounting : • Budgeting • Job order costing • Process costing • Cost of goods sold Financial management : • Capital budgeting • Net Present Value (NPV) • Internal Rate of Return (IRR) • Payback period • Discounted cash flows • Financial analysis • Capital assets pricing model • Simple interest, Compound interest & annuities
4.40+
65+ Reviews
86+ Question Solved
Related Book For
Accounting Information Systems
ISBN: 9781266370373
4th Edition
Authors: Vernon Richardson, Chengyee Chang, Rod Smith
Question Posted:
Students also viewed these Business questions
-
1. Which phase of the systems development life cycle would include a feasibility analysis? a. Analysis phase b. Planning phase c. Design phase d. Implementation phase 2. The IFAC suggested 10 core...
-
Let r and s be solutions to the quadratic equation x 2 b x + c = 0. For n N, define d0 = 0 d1 = r s dn = b dn1 c dn2 (n 2) Prove that dn = r n s n for all n N. [4 marks] (b) Recall that a commutative...
-
HOME WORK DEADLINE TOMORROW Misdirecting 48. Lee De Forest upheld a vacuum tube that inside and out better the improvement of the volume of the sound-on-plate process. A. Authentic B. Beguiling 49....
-
Decedent died owning an insurance policy that would pay $2 million to Beneficiary. Six months later, the insurance company paid Beneficiary $2 million plus $50,000 interest. What portion of the...
-
A critic recently claimed that hedge funds cause market volatility to increase when they publicize (and document) that a public corporation exaggerated its earnings. The critic argued that hedge...
-
In Figure P33.22, a straight plank of lumber enters a pool of water at an angle. What does the plank look like to the observer? Data from Figure P33.22 air water plank actual position
-
Which of the following procedures would likely lend insight into the risk of material misstatement arising from violations of laws and regulations? a. Confirming receivables balances with debtors. b....
-
Utease Corporation has many production plants across the midwestern United States. A newly opened plant, the Bellingham plant, produces and sells one product. The plant is treated, for responsibility...
-
Need help with SQL homework, questions start under the problems section. This document is intended to relate the concepts we discuss in class to the Oracle SQL Language Reference or to the Oracle...
-
The SarbanesOxley Acts section 404 reports require management and auditors to report on: a. the financial condition of the firm. b. the quality of the project management planning. c. the academic...
-
The 100% rule suggests that before a PERT chart is done, a project manager must: a. make sure 100 percent of the project is funded. b. make sure the project team is devoted solely, or 100 percent, to...
-
For each situation (a-d) in Exercise 8.37, state which of the following three forms of the rejection region is appropriate when Ï is known. R:X sc (left-sided) R: X c right-sided) R: |X-0 c...
-
We regret to announce that we can offer the 50 percent discount only to the the first 25 buyers, so act quickly! Revise the following statements to make them more positive and courteous.
-
Which aspects of a business may be detailed by a BPMN diagram? Which may be detailed by a state machine diagram?
-
Develop a library based on the functions that we have considered in this book for computing properties of integers. Include functions for determining whether a given integer is prime; determining...
-
Using the St. Louis Fed website (FRED), chart the Merrill Lynch HighYield (speculative grade) Master II optionadjusted corporate bond spread. How has it behaved over the business cycle?
-
Prepare a flowchart on obtaining an injunction (or restraining order) against violence threatened by a husband against his wife in your state.
-
Is it fair that Robins Wood does not get a chance to defend itself based on the actions of one employee?
-
Calculate Total Contribution Margin for the same items. Total Revenue Total Variable Costs Total Contribution Margin $50.00 a. $116.00 $329.70 b. $275.00 $14,796.00 $7,440.00 c. $40,931.25 d....
-
Study Figure showing the level 0 DFD of the cost accounting system for a company using standard costing. Redraw Figure assuming that the company uses an actual cost instead of a standard costsystem....
-
Study Figure showing the level 0 DFD of the cost accounting system for a company using standard costing. Redraw Figure assuming that the company uses an actual cost instead of a standard costsystem....
-
Figure shows several data flows running to the general ledger (GL) for the purpose of updating the GL master data. a. For each of the following data flows in Figure show the journal entry (in...
-
Explain the concept of strategic HRM. (1.2) Explain the meaning of strategic HRM Discuss the benefits of strategic HRM.
-
There are factors inside of a country that impacts HRM, as well as factors outside of a country that can impact HRM. For example, the laws of one country, in terms of labor union membership, can...
-
During the year, TRC Corporation has the following inventory transactions. Date January 1 Transaction Beginning inventory April 7 Purchase July 16 Purchase October 6 Purchase Number of Unit Total...
Study smarter with the SolutionInn App