Given the set of activities indicated in the table below, construct a network diagram with the expected

Question:

Given the set of activities indicated in the table below, construct a network diagram with the expected duration and the critical path:

Task Predecessor Duration A — 10 B — 8 C B 1 D A, C 8 E D 3 F E 2 G — 3 H D, G 1 I H 1 J E 1 K I, J 2 L D 2 LO.1