The following table provides the crash data for the network project described in Problem 12: Activity Time
Question:
The following table provides the crash data for the network project described in Problem 12:
Activity Time (weeks) Activity Cost Activity Normal Crash Normal Crash a 9 7 $4,800 $ 6,300 b 11 9 9,100 15,500 c 7 5 3,000 4,000 d 10 8 3,600 5,000 e 1 1 0 0 f 5 3 1,500 2,000 g 6 5 1,800 2,000 h 3 3 0 0 i 1 1 0 0 j 2 2 0 0 k 8 6 5,000 7,000 The normal activity times are considered to be deterministic and not probabilistic. Using the computer, crash the network to 26 weeks. Indicate how much it would cost the bank and then indicate the critical path. LO.1
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: