A customer requests the production of a product from the company in question 9 above. The company

Question:

A customer requests the production of a product from the company in question 9 above. The company estimates its direct labour and material costs will be £30 and £90, respectively. The job will pass through each of the three machine groups, spending 4 hours in group 1, 7 hours in group 2, and 5 hours in group 3.

Required:

Prepare a job cost sheet for the above job, showing clearly the prime and factory cost of manufacture.

Question 9

A company has three different groups of machines for which it wishes to establish machine rates. A budget for the year ending 31 December 1985 shows the following overhead:

image text in transcribed

Additional information available:

image text in transcribed