There are four activities along the critical path for a project. The expected values and variances of

Question:

There are four activities along the critical path for a project. The expected values and variances of the completion times of the activities are listed here. Determine the expected value and variance of the completion time of the project.

Expected Completion Activity Time (Days) Variance 1 18 8 2 12 5 3 27 6 4 8 2