There are four activities along the critical path for a project. The expected values and variances of
Question:
There are four activities along the critical path for a project. The expected values and variances of the completion times of the activities are listed here. Determine the expected value and variance of the completion time of the project.
Expected Completion Activity Time (Days) Variance 1 18 8 2 12 5 3 27 6 4 8 2
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Statistics For Management And Economics
ISBN: 9781133420774
9th Edition
Authors: Gerald Keller, Kenneth C Louden
Question Posted: