Suppose that a batch of parts is plated with copper in an electrolytic bath running at 0.15

Question:

Suppose that a batch of parts is plated with copper in an electrolytic bath running at 0.15 V and 15.0 A for exactly 2 hours. What is the energy cost of this process if the electric utility charges the company $0.0500 per kWh?

Strategy 

We can determine the energy expended because we know the current, time, and voltage. The current multiplied by the time gives us the charge, which when multiplied by the voltage yields the energy. Once we know the energy expenditure we can convert the value we calculate (in J) to kWh to obtain the cost of the electricity.