A company is examining two mutually exclusive projects. Project P requires an immediate investment of $225,000 and
Question:
a. Calculate the IRR of each project. On the basis of their IRRs, which project is preferred?
b. Which project should be selected if the firm’s cost of capital is 16%?
c. Which project should be selected if the firm’s cost of capital is 13%?