Your company has been hired to act as a construction manager for the construction of a bookstore
Question:
Your company has been hired to act as a construction manager for the construction of a bookstore for a fixed fee of $32,000. When the design was 90% complete, you prepared a budget for the project, which is shown in Figure 4-13. During the buyout, the subcontracts shown in Figure 4-14 were signed and the purchase orders shown in Figure 4-15 were issued. No additional costs are expected for the contracts in Figure 4-14 and the purchase orders in Figure 4-15. A purchase order has been issued for concrete for $115 per cubic yard. This price is 4% below the costs used in the budget.
In Figure 4-14
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Accounting And Financial Management
ISBN: 9780132675055
3rd Edition
Authors: Steven J. Peterson
Question Posted: