The Lee Street case study project did not include a formal finishes schedule in the contract documents,

Question:

The Lee Street case study project did not include a formal finishes schedule in the contract documents, as the builder was also the developer and the finishes evolved as the building was constructed.

Utilize the photographs and drawings from the book’s eResource and prepare a CSI 08 or 09 OM recap for one of these executive townhomes.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Construction Cost Estimating

ISBN: 9780367902681

1st Edition

Authors: John E. Schaufelberger, Len Holm

Question Posted: