What is the cost of a 20 FT 20 FT 8 FT concrete tower crane
Question:
What is the cost of a 20 FT × 20 FT × 8 FT concrete tower crane footing based on the following parameters? The process to be used is similar to the process described in Chapter 6 for quantity take-off of a spot footing and the pricing process described in Chapter 11. Make sure you perform a $/MH and $/CY check when you are done. Make whatever assumptions are necessary.
a. Formwork material cost at $2/SFCA and 0.5 MH/SFCA.
b. Concrete purchase including pumping at $150/CY.
c. Rebar tonnages at 200 LBs/CY.
d. Rebar purchase and install costs at $1,000/ton.
e. Rebar template at $100 for material plus one-hour labor.
f. Eight tower crane anchor bolts at $5,000.
g. Overhead and profit at 20%.
h. Excavation and backfill at $1,550.
Step by Step Answer:
Construction Cost Estimating
ISBN: 9780367902681
1st Edition
Authors: John E. Schaufelberger, Len Holm