7. The developer of a 40-story high-rise office building desires the shortest possible construc- tion time. What
Question:
7. The developer of a 40-story high-rise office building desires the shortest possible construc-
tion time. What delivery method would be best?
a. Design/bid/build
b. Design/build
c. Construction project management
d. All of the above
e. Choices b and c only