A project has three phases, concept, development, and launch, that are expected to cost $5M, $15M, and
Question:
A project has three phases, concept, development, and launch, that are expected to cost $5M, $15M, and $4M, respectively. The likelihoods of success for the three phases are 0.5, 0.8, and 0.7, respectively. If the estimated NPV of future earnings is $90M, what is the ECV for the project?
[Answer: $11.1 M.]