A project manager facilitates a meeting with the project team to review an assessment of risks recently

Question:

A project manager facilitates a meeting with the project team to review an assessment of risks recently completed. During this meeting, they evaluate options for responding to the risks. It is decided that two risks will not receive any action and that they will deal with the consequences at the time of occurrence, should they occur. What type of risk response is this?

A. Passive acceptance B. Active acceptance C. Mitigation D. Avoidance