A project manager has four crews that can be hired on a temporary basis during peak construction
Question:
A project manager has four crews that can be hired on a temporary basis during peak construction periods. The manager currently has three projects more than can be handled with his regular crews. It is desired to determine the crew assignments that will minimize the total project cost. The costs of using certain crews for certain projects are presented as follows:
Crew 1 Project A: \(\$ 4,000\)
Project B: \(\$ 3,000\)
Project C: \(\$ 9,000\)
Crew 2 Project A: \(\$ 7,000\)
Project B: \(\$ 1,000\)
Project C: \(\$ 8,000\)
Crew 3 Project A: \(\$ 2,000\)
Project B: \(\$ 6,000\)
Project C: \(\$ 4,000\)
Crew 4 Project A: \(\$ 9,000\)
Project B: \(\$ 5,000\)
Project C: \(\$ 5,000\)
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 272859
2nd Edition
Authors: Adedeji B. Badiru
Question Posted: