Question: A project manager is responsible for performance reporting. Which of the following is not one of the tools and techniques that the project manager can
A project manager is responsible for performance reporting. Which of the following is not one of the tools and techniques that the project manager can use for performance reporting?
a. Variance analysis
b. Earned value reports
c. Performance reviews
d. Past project review