A project manager wants to subcontract part of the project. This part of the project is quite

Question:

A project manager wants to subcontract part of the project. This part of the project is quite complicated, and there are many ways that the work can be done. What method of solicitation should be used by the project team?

a. Request for bid

b. Request for quotation

c. Request for proposal

d. Request for information