(a) Using PERT, calculate expected project duration and determine the critical path in the network defined by...
Question:
(a) Using PERT, calculate expected project duration and determine the critical path in the network defined by the data below.
(b) What is the probability of completing this project in 32 weeks or less?
Transcribed Image Text:
Activity 10 20 30 40 50 60 70 80 90 100 110 120 130 140 Description Prefab Wall Forms Excavate Cols and Walls Let Elec and Mech Subcontract Deliver Wall Forms Forms, Pour & Cure Wall & Col Fig Rough-in Plumbing Install Conduit Erect Wall Forms & Steel Fabricate & Set Interior Column Forms Erect Temporary Roof Pour, Cure & Strip Walls Pour, Cure & Strip Int. Walls Backfill for Slab on Grade Grade & Pour Floor Slab Type Constant Constant Constant m Tas Im Ib Constant Constant Constant Constant Constant Constant Duration (Weeks) 2 3 3, 4, 8 4 6,7,8 5, 7, 10 9, 11, 15 9 6 12, 16, 18 10 6 1 5 Successor 40 50, 60, 70 60, 70 80, 90, 100 80, 90, 100 110 110 110 120 140 130 140 140 END
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Answer rating: 50% (2 reviews)
Answered By
Mehwish Aziz
What I have learnt in my 8 years experience of tutoring is that you really need to have a friendly relationship with your students so they can come to you with their queries without any hesitation. I am quite hardworking and I have strong work ethics. Since I had never been one of those who always top in the class and always get A* no matter what, I can understand the fear of failure and can relate with my students at so many levels. I had always been one of those who had to work really hard to get decent grades. I am forever grateful to some of the amazing teachers that I have had who made learning one, and owing to whom I was able to get some extraordinary grades and get into one of the most prestigious universities of the country. Inspired by those same teachers, I am to be like one of them - who never gives up on her students and always believe in them!
5.00+
3+ Reviews
10+ Question Solved
Related Book For
Construction Management
ISBN: 9781119256809
5th Edition
Authors: Daniel W. Halpin, Bolivar A. Senior, Gunnar Lucko
Question Posted:
Students also viewed these Business questions
-
The project network and table below show the expected number of weeks to complete a series of activities and the corresponding variances: a. Determine the critical path and the earliest expected...
-
The Stone River Textile Mill was inspected by OSHA and found to be in violation of a number of safety regulations. The OSHA inspectors ordered the mill to alter some existing machinery to make it...
-
can someone solve this Modern workstations typically have memory systems that incorporate two or three levels of caching. Explain why they are designed like this. [4 marks] In order to investigate...
-
Draw the Lewis structure of AlH 3 . Strategy Draw the Lewis structure in the normal way but realize that, in certain cases, it is not possible to place eight electrons around the central atom.
-
What happens when a person has too much money? What about when an economy has too much money?
-
Question 24 1 pts If the industry average Current Ratio is 2.5 and the industry average Quick Ratio is 1.5, Country Kettles' liquidity compared to the industry is better. O worse. O indeterminate (or...
-
NCAA rules for athletes. The National Collegiate Athletic Association (NCAA) requires Division II athletes to get a combined score of at least 820 on the Mathematics and Critical Reading sections of...
-
a. Calculate the centroids for each group in the analysis sample. What do these values indicate? b. Use the regression approach to two-group DA to develop a rule for predicting whether or not a...
-
2. A steel pedestrian overpass must either be reinforced or replaced. Reinforcement would cost $25,000 and would make the overpass adequate for an additional 6 years of service. If the overpass is...
-
(a) Given the data below for a small pipeline project, based on a PERT analysis what is the expected project duration? (b) What is the probability of completing this project in 120 days or less?...
-
Why is it that all critical activities have TF of 0? Consider the definition of TF in your response.
-
The unadjusted trial balance of PS Music as of July 31, 2014, along with the adjustment data for the two months ended July 31, 2014, are shown below. Based upon the adjustment data, the adjusted...
-
Ted sold his Microsoft stock for $40,000 paying a commission of $800. He purchased the stock in 2004 for $8,000 and paid commission of $200. What is the recognized gain on the sale?
-
Liquid water at 80C and at 1atm flows through a heated pipe at a flow rate of 3.1 kg/s. It then leaves the pipe as steam. The water receives 9753840 J of heating from the pipe. Calculate the...
-
The balance sheet of River Electronics Corporation as of December 31, 2023, included 14.00% bonds having a face amount of $90.7 million. The bonds had been issued in 2016 and had a remaining discount...
-
The term mutually exclusive means that two events have no common elements in them. The occurrence of one event means that the other other event does not occur. An example of a mutually exclusive...
-
9a A conical pendulum is made by hanging a mass of 5.0 kg from a large spring of length 1.0 m and spring constant k = 100 N/m. The spring moves in a circle at an angle of 25 deg. When at rest hanging...
-
Use Method 2 (i.e., Always Remember That There Are Only Two Rates, and You Will Always Get the Disadvantageous One) to explain whether the bid rate or ask rate should be used for each of the four...
-
Repeat the previous problem, but close the positions on September 20. Use the spreadsheet to find the profits for the possible stock prices on September 20. Generate a graph and use it to identify...
-
Which type(s) of contract relies on the measurement of approximate (as opposed to actual) quantities completed during each pay period?
-
Give two reasons why owners retain funds from a contractor's pay requests.
-
You are a subcontractor and have furnished the windows on a job but have not been paid. What can you do? What additional recourse does the prime contractor have?
-
Minden Company introduced a new product last year for which it is trying to find an optimal selling price. Marketing studies suggest that the company can increase sales by 5,000 units for each $2...
-
Prepare the adjusting journal entries and Post the adjusting journal entries to the T-accounts and adjust the trial balance. Dresser paid the interest due on the Bonds Payable on January 1. Dresser...
-
Venneman Company produces a product that requires 7 standard pounds per unit. The standard price is $11.50 per pound. If 3,900 units required 28,400 pounds, which were purchased at $10.92 per pound,...
Study smarter with the SolutionInn App