An Agile project team builds their schedule by pulling features from the backlog reflected on a task

Question:

An Agile project team builds their schedule by pulling features from the backlog reflected on a task board as capacity to take on work becomes available. In some cases, a feature may take two weeks to complete, while in others, it takes more. What type of delivery method does this describe?

A. Waterfall B. Iteration-based Agile C. Scrum D. Flow-based Agile