Answer the following questions using the tabulated project data. (a) There is a penalty of $3000/day beyond
Question:
Answer the following questions using the tabulated project data.
(a) There is a penalty of $3000/day beyond the normal PERT duration. Perform a crashing analysis to compare total normal cost to total crash cost. First crash only the critical activities; then crash all activities.
(b) Find the probability that the total lateness penalty will be less than $3000.
(c) Find the probability that the total lateness penalty will be $3000 or less.
(d) Find the probability that the total lateness penalty will be greater than $3000.
(e) Find the probability that the total lateness penalty will be less than $9000.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Systems Principles And Applications
ISBN: 9781420083200
1st Edition
Authors: Adedeji B Badiru
Question Posted: