Answer the following questions using the tabulated project data. (a) There is a penalty of $3000/day beyond

Question:

Answer the following questions using the tabulated project data.image text in transcribed

(a) There is a penalty of $3000/day beyond the normal PERT duration. Perform a crashing analysis to compare total normal cost to total crash cost. First crash only the critical activities; then crash all activities.

(b) Find the probability that the total lateness penalty will be less than $3000.

(c) Find the probability that the total lateness penalty will be $3000 or less.

(d) Find the probability that the total lateness penalty will be greater than $3000.

(e) Find the probability that the total lateness penalty will be less than $9000.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: