Consider the road job described in Figure 9.5, which consists of 14 road sections to be completed.

Question:

Consider the road job described in Figure 9.5, which consists of 14 road sections to be completed. The objective chart for this job is given. Assume that each month consists of 20 working days on average. The program chart for this process is also shown. Calculate the LOB for the study representing the beginning of month 9 (i.e., day to right of number 8).